Resource-Constrained Project Scheduling

This demo solves a Resource-Constrained Project Scheduling Problem (RCPSP) and compares three solvers side-by-side: HiGHS (MILP), SCIP (MILP), and D-Wave's Stride hybrid solver. RCPSP is a canonical combinatorial optimization problem in the operations research and scheduling domains and is NP-hard in general.

The included instance (30n20b8.mps) has 30 jobs, 2 renewable resource types (mechanics and technicians), and up to 3 execution modes per job. The known optimal objective value is 302.

Demo Example Demo Solution Example

Installation

You can run this example without installation in cloud-based IDEs that support the Development Containers Specification (aka "devcontainers") such as GitHub Codespaces.

For development environments that do not support devcontainers, install requirements:

pip install -r requirements.txt

If you are cloning the repo to your local system, working in a virtual environment is recommended.

Usage

Your development environment should be configured to access the Leap™ quantum cloud service. You can see information about supported IDEs and authorizing access to your Leap account here.

Run the following terminal command to start the Dash application:

python app.py

Access the user interface with your browser at http://127.0.0.1:8050/.

The demo program opens an interface where you can configure problems and submit these problems to a solver.

Configuration options can be found in the demo_configs.py file.

Note

If you plan on editing any files while the application is running, please run the application with the --debug command-line argument for live reloads and easier debugging: python app.py --debug

Problem Description

A set of jobs must be scheduled on a project timeline. Each job must be executed in exactly one mode, where each mode specifies a duration and a resource consumption rate. Faster modes consume more resources per time unit. Jobs have precedence constraints: a job cannot start until all of its predecessors have finished. Two shared resource pools (mechanics and technicians) are consumed while jobs are active, and the project manager must decide how large each pool to hire. Hiring is paid for by the whole project, so the goal is to minimize total workforce cost while still satisfying every precedence and resource constraint.

Objective: Minimize the total cost of hired mechanics and technicians:

100 · R_M + 51 · R_T

Constraints:

  • Each job is executed in exactly one mode.
  • A job's start time respects all predecessor finish times (precedence).
  • At every point in time, the active resource consumption of all running jobs cannot exceed the hired pool size for each resource type.
  • The hired pool sizes are bounded by market availability (40 mechanics, 30 technicians).

Model Overview

Parameters

Symbol Description
J Set of jobs (30 in the provided instance)
M_j Set of execution modes for job j (up to 3)
d_jm Duration of job j in mode m (time units)
r^M_jm Mechanic units consumed per time unit by job j in mode m
r^T_jm Technician units consumed per time unit by job j in mode m
prec Set of precedence pairs (j₁, j₂): j₁ must finish before j₂ starts
R̄_M = 40 Maximum mechanics available for hire
R̄_T = 30 Maximum technicians available for hire

Variables

Symbol Type Description
x_jmt ∈ {0,1} Binary (MILP) 1 if job j starts at time t in mode m
S_j ∈ ℤ≥0 Integer Start time of job j
m_j ∈ {1,2,3} Integer Execution mode of job j
R_M ∈ {0,...,40} Integer Number of mechanics hired
R_T ∈ {0,...,30} Integer Number of technicians hired

The MILP formulations (HiGHS and SCIP) operate on the time-indexed binary variables x_jmt. The Stride nonlinear formulation uses S_j and m_j directly as integer decision variables, producing a much more compact model.

Objective

min  100 · R_M + 51 · R_T

Constraints

Job execution (each job runs in exactly one mode at exactly one start time):

∑_(m ∈ M_j) ∑_t  x_jmt = 1   for all j ∈ J

Precedence (job j₂ cannot start until j₁ finishes):

S_j₁ + d_(j₁, m_j₁)  ≤  S_j₂   for all (j₁, j₂) ∈ prec

Resource capacity (active consumption never exceeds the hired pool):

∑_(j ∈ J) r^M_jm_j · 1[S_j ≤ t < S_j + d_(j,m_j)]  ≤  R_M   for all t

∑_(j ∈ J) r^T_jm_j · 1[S_j ≤ t < S_j + d_(j,m_j)]  ≤  R_T   for all t

Code Overview

app.py                  Dash application entry point
demo_callbacks.py       All Dash callback functions (solver dispatch, results rendering)
demo_configs.py         UI configuration constants and known optimal values
demo_interface.py       Dash layout builders and reusable component functions
src/
  highs.py             HiGHS MILP solver wrapper
  scip.py              SCIP MILP solver wrapper
  stride.py            D-Wave Stride nonlinear model and solver wrapper
  plot.py              Plotly figure builders (input view, solution view, comparison)
  demo_enums.py        SolverType enum
  demo_runner.py       Parallel run orchestration and result summarization
  utils.py             MPS file parser and MILP variable-name decoder shared across solvers and plot builders
input/
  30n20b8.mps          Benchmark RCPSP instance in MPS format

Three solver formulations are compared on the same instance:

  • HiGHS (MILP) — reads the MPS file directly using highspy. Uses the classical time-indexed binary formulation where x_jmt is a binary variable for every (job, mode, start-time) triple. Scales poorly with horizon length but is a well-understood baseline.

  • SCIP (MILP) — same MPS file via PySCIPOpt. SCIP's branch-and-bound and cutting-plane machinery often finds better bounds than HiGHS within the same time limit on hard instances.

  • Stride Hybrid Solver — a compact nonlinear model built with dwave.optimization. Start times and modes are integer decision variables; resource feasibility is enforced with a sweep-line (AccumulateZip) over sorted event times rather than per-timestep constraints. This dramatically reduces model size and is submitted to LeapHybridNLSampler.

Input visualization (plot.py / build_input_graph) displays an ASAP (As-Soon-As-Possible) schedule computed by a topological-order forward pass on the precedence graph, ignoring resource limits. This shows the theoretical lower bound on makespan and the resource demand profile before any resource-feasibility adjustments are made.

Solver comparison runs each selected solver the requested number of times and records the objective value, feasibility flag, and best schedule per run. Results populate the per-solver tabs (Gantt + resource demand) and a Results summary tab with a cross-solver demand comparison and an objective-value table.

References

The instance 30n20b8.mps is from the MIPLIB 2017 benchmark collection: miplib.zib.de/instance_details_30n20b8.html

License

Released under the Apache License 2.0. See LICENSE file.

About

Compare objective values for three formulations on the same RCPSP instance.