Agentic Earned Value (AEV)

DOI Tests

Earned Value Management for software programs where AI agents do part of the work.

AEV was first defined by Gunpreet Sabharwall (ORCID 0009-0000-5434-7382), 2026.

Classic EVM assumes people do the work. When AI agents write code, new costs (model usage, compute, human review) and new risks (work that gets reverted) appear. AEV keeps CPI, SPI and EAC, and adds:

  1. Blended Actual Cost: agent and review costs included
  2. Rework-adjusted Earned Value: value taken back if work is reverted
  3. Attribution: efficiency by human, agent, or mixed work

📄 Method note: AEV-method-note-v0.1.md

Status

  • v0.1: method definition.
  • v0.2.0: reference GitHub Action. Add one workflow file to any public repository and get a weekly AEV-REPORT.md and a CPI badge. See CHANGELOG.md.

Try it in 1 minute (no GitHub setup needed)

The demo runs on sample data in examples/demo/ and reproduces the worked example in section 5 of the method note.

You need Python 3.11 or newer. In a terminal, from the top folder of this repository:

pip install -r requirements.txt
PYTHONPATH=src python -m aev --demo

The report is printed and saved to examples/demo/AEV-REPORT.md. You can also just read the saved demo report.


Quick start: add AEV to your repository

You do this once. It takes about 10 minutes and all of it can be done in the GitHub website.

Step 1: Copy one workflow file

In your repository, create the file .github/workflows/aev.yml with exactly this content (also in examples/aev.yml):

name: AEV report

on:
  schedule:
    - cron: "17 6 * * 1"   # every Monday at 06:17 UTC
  workflow_dispatch:        # adds a "Run workflow" button on the Actions tab

permissions:
  contents: write           # to commit AEV-REPORT.md and .aev/badge.json
  issues: read              # to read issue labels and history
  pull-requests: read       # to read linked pull requests

jobs:
  aev:
    runs-on: ubuntu-latest
    steps:
      - uses: actions/checkout@v4
      - uses: GunpreetSabharwall/agentic-earned-value@v0.2.0

No password or personal token is needed. GitHub gives the workflow a temporary token automatically.

Step 2: Add the settings folder

Create a folder called .aev at the top of your repository with three files. You can copy them from examples/starter/.aev/.

.aev/config.yml: your budget and plan

budget_at_completion: 100000   # total planned budget for the work (money)
value_per_point: 1000          # an issue labelled "aev-points:3" is worth 3 x this
start_date: 2026-01-05         # planned value starts at 0 on this date (YYYY-MM-DD)...
end_date: 2026-03-16           # ...and reaches the full budget on this date
hourly_rate: 100               # cost of one hour of human time (money)
stabilization_window_days: 14  # work reopened or reverted within this many days is taken back
agent_accounts:                # GitHub logins of your AI agents / bots
  - my-coding-agent[bot]

.aev/hours.csv: human time. One line per entry. item is the issue number (or leave it blank). type is build (doing the work) or review (reviewing or correcting agent work).

date,item,type,hours
2026-01-12,14,build,6
2026-01-13,15,review,1.5
2026-01-13,,review,2

.aev/agent-costs.csv: money spent on agents. category is one of model, compute, ci, tools.

date,item,category,amount
2026-01-12,15,model,42.50
2026-01-31,,ci,120

You can edit these CSV files in the GitHub website or in any spreadsheet program (save as CSV).

Step 3: Label your issues

Give each issue a label aev-points:N, where N is its size in points. For example aev-points:3. The issue's budgeted value is N × value_per_point.

To create labels: go to your repository → Issues → Labels → New label, and create, for example, aev-points:1, aev-points:2, aev-points:3, aev-points:5, aev-points:8.

Link each pull request to its issue, for example by writing Fixes #14 in the pull request description.

Step 4: Run it

Go to Actions → AEV report → Run workflow. After about a minute, AEV-REPORT.md appears at the top of your repository. After that it updates every Monday by itself.

Optional: show the CPI badge

Add this line to your README, replacing OWNER/REPO with your repository:

![AEV CPI](https://img.shields.io/endpoint?url=https://raw.githubusercontent.com/OWNER/REPO/main/.aev/badge.json)

The badge is green when CPI is 1.00 or more, yellow from 0.90 to 0.99, and red below 0.90.

Action options

All are optional.

Option Default What it does
config .aev/config.yml Where your settings file is. The CSV files are read from the same folder.
output AEV-REPORT.md Where the report is written.
badge .aev/badge.json Where the badge file is written.
commit true Set to false to skip committing the report (it still appears in the workflow run summary).
demo false Set to true to run on the sample data instead of your repository.

Example: with: { commit: "false" } under the uses: line.


How AEV is calculated

The full definition is in the method note. In short:

Term How this tool gets it
PV (planned value) Grows in a straight line from 0 on start_date to budget_at_completion on end_date.
Accepted Issue closed as completed and at least one linked pull request merged.
Clawback An accepted issue is reopened, or one of its pull requests is reverted, within stabilization_window_days of acceptance.
EV Gross EV (value of accepted issues) − Clawback.
AC AC_build (build hours × rate) + AC_review (review hours × rate) + AC_agent (agent costs).
CPI, SPI, EAC EV / AC, EV / PV, AC + (BAC − EV) / CPI.
Rework Rate Clawback / Gross EV.
Agent Cost Share AC_agent / AC.
Review Load Ratio AC_review / AC_agent.
Authorship class A if all merged pull requests on the issue are by agent_accounts, H if none are, M if mixed. CPI is shown for each class.

If a number cannot be calculated (for example, CPI when nothing has been spent yet), the report shows n/a.

The report also shows a Classic EVM column (build labor only, no clawback) next to AEV, so you can see what classic EVM would have told you.

How the code is organised

Folder / file What is in it
action.yml The GitHub Action other repositories use.
src/aev/formulas.py Every AEV formula, one small function each.
src/aev/items.py Rules for accepted, clawback and authorship class.
src/aev/calculator.py Puts the formulas together.
src/aev/github_data.py Reads issues and pull requests from GitHub (the only part that talks to GitHub).
src/aev/report.py Writes AEV-REPORT.md and the badge.
tests/ Automated tests, including the method note's worked example.
examples/ Demo data, starter settings and the workflow file to copy.

To run the tests: pip install -r requirements-dev.txt then python -m pytest.


Limitations

  • Costs are entered by hand in v0.1. Hours and agent costs come from .aev/hours.csv and .aev/agent-costs.csv. There is no automatic import from billing or time-tracking tools yet.
  • Review time is self-reported. AC_review is only as accurate as the hours people record.
  • "Required checks passed" is not checked separately. A merged pull request is taken as having passed its checks. Use branch protection if you need that guarantee.
  • Reverts are found by GitHub's standard "Revert" button text (Reverts owner/repo#123). Reverts made by hand in other ways are not detected; reopening the issue still triggers a clawback.
  • Planned value is a straight line between the start and end dates.
  • Public repositories are the target. Private repositories work too, as long as the workflow has the permissions shown above.
  • If your default branch is protected so that workflows cannot push, set commit: "false". The report is still shown in each workflow run's summary.
  • The example numbers are illustrative. See section 7 of the method note for the method's own limitations.