Skip to content

refactor(driver-sql): move the deferred-DDL previews out of sql-driver.ts into sql-driver-schema-sync.ts (#25521 cut 18) #51955

refactor(driver-sql): move the deferred-DDL previews out of sql-driver.ts into sql-driver-schema-sync.ts (#25521 cut 18)

refactor(driver-sql): move the deferred-DDL previews out of sql-driver.ts into sql-driver-schema-sync.ts (#25521 cut 18) #51955

Re-run triggered October 27, 2026 20:25
Status Success
Total duration 12m 40s
Artifacts 3

ci.yml

on: pull_request
Build UI Deps
Build UI Deps
Plan Test Core shards
1m 56s
Plan Test Core shards
Matrix: dogfood
Dogfood Verify CLI
Dogfood Verify CLI
Temporal Conformance (live PG + MySQL)
Temporal Conformance (live PG + MySQL)
Build Core
6m 50s
Build Core
Build Docs
Build Docs
Matrix: test-ui
Type Check UI
Type Check UI
Lint UI
Lint UI
Build & E2E UI
Build & E2E UI
Matrix: test
Dogfood Regression Gate
32s
Dogfood Regression Gate
Fit to window
Zoom out
Zoom in

Annotations

2 warnings and 3 notices
Suite-duration ceiling
@objectstack/service-package: 34.34s, over its 32.90s ceiling. Slowest file: src/install-primitive-declaration.test.ts 1.83s. Report only, on every event (this is a `pull_request` run): a suite's wall on a shared runner measures the run's load as much as the package, so this is a reading, not a failure.
Suite-duration ceiling
@objectstack/organizations: 140.98s, over its 137.91s ceiling. Slowest file: src/storage-upload-organization-change.wall.test.ts 8.71s. Report only, on every event (this is a `pull_request` run): a suite's wall on a shared runner measures the run's load as much as the package, so this is a reading, not a failure.
Turbo remote cache disabled (Test Core (6/8) closure)
Remote caching disabled (remote cache requested — set TURBO_TOKEN and TURBO_TEAM, or run "turbo login" and "turbo link") -- expected: the remote-cache credentials are passed only to merge_group runs and runs on main, so this run built from the restored Actions-cache seed.
Test Core (6/8)
"The ubuntu-latest label will migrate to Ubuntu 26 beginning October 19, 2026. For more information, see https://github.com/actions/runner-images/issues/14748"
Test Core
"The ubuntu-latest label will migrate to Ubuntu 26 beginning October 19, 2026. For more information, see https://github.com/actions/runner-images/issues/14748"

Artifacts

Produced during runtime
Name Size Digest
test-core-timing-table
106 KB
sha256:04aa86c1249137c7c0298510e394eca062d9765429dc44ffb3abe893310c2a2a